Wondering how long a kitchen remodel takes in Oregon? Learn the typical timeline, what affects it, and how The Build Well Process keeps your project on track.

Most Oregon homeowners want to know one thing before starting a kitchen remodel: How long is this going to take?

On average, a full kitchen remodel in Lake Oswego, West Linn, Wilsonville, Tualatin, or Woodburn takes 6–12 weeks, depending on the scope, design decisions, and structural work.

Here’s what the process really looks like.

Typical Kitchen Remodel Timeline

  • Planning & Design: 2–6 weeks
    • This is where decisions happen: layout, materials, cabinetry, countertops, appliances.
  • Permitting: 1–4 weeks
    • Varies by city and scope. Structural changes = longer wait.
  • Demo: 2–5 days
  • Rough-In Work: 1–3 weeks
    • Electrical, plumbing, framing adjustments.
  • Drywall, Texture & Paint: 1–2 weeks
  • Cabinets & Countertops: 2–4 weeks
    • Countertops require templating after cabinets are installed.
  • Flooring, Backsplash & Details: 1–2 weeks
  • Final Touches & Inspection: 1 week

What Delays a Kitchen Remodel?

  • Custom cabinets often drive timelines because they’re built to order. Lead times can stretch several weeks or more, and any changes after production starts can push delivery back even further.
  • Specialty materials like stone countertops, custom tile, or imported fixtures depend on availability and fabrication schedules. If something is backordered or arrives damaged, installs may need to be rescheduled.
  • Structural changes take time because they require planning, inspections, and the right sequence of work. Moving walls or utilities isn’t instant and can’t be rushed without compromising safety.
  • Permit backlog are outside a contractor’s control. Local jurisdictions can take longer than expected to review and approve plans, especially during busy seasons.
  • Homeowner design changes mid-project, even small ones, often create ripple effects. New selections can require revised plans, reorders, or additional inspections, which adds time.

How the Build Well Process Keeps Things on Track

Our Pre-Construction Agreement ensures schedules, selections, and plans are finalized before the demo begins — which protects your timeline.